  1. S

    Norwegian 60kwh Powerwall SI8.0 REC BMS Leaf cells

    Time to update the thread a bit. Things have been slow due to several other projects on the house. But set aside some time this week, an are now finished with dc side. 147 modules, bms leads, shunt, contactor, precharge, abb breaker and sma inverter wired. Went with 200a fuses, but do consider...
  2. S

    Battery balancing before connecting in parallel

    Yeah, had a nut that broke the inside plastic, so screw and nut is just turning freely. Screw is well inside the nut, so i will make a copper wedge to ensure good contact. This was just to verify the connection :)
  3. S

    Battery balancing before connecting in parallel

    Connected now, everything went fine! Thanks for all the support :)
  4. S

    Battery balancing before connecting in parallel

    Hi, i actually remebered a little wrong: they are 3.88 and 3.98. (and 7.76 and 7.97 across the 2+2 leaf setup. So its within 0.1v
  5. S

    Battery balancing before connecting in parallel

    Hi, I have sorted my nissan leaf cells, and are more or less ready to connect the parallell bus bar. I have batteries from 3 cars, where 2 of them are 3.98v now and the last 3.79v pr cell. Is this too high difference to connect? Should I charge up/drain to get them more equal? How much diff...
  6. S

    Norwegian 60kwh Powerwall SI8.0 REC BMS Leaf cells

    Yes, of course. On AC side, the inverter will be secured with a 40a fuse @230v. (max 9200w, and be limited to this in the software) Im thinking to protect the wires, but also internally in the batteries between the series, see the picture in first post.
  7. S

    Norwegian 60kwh Powerwall SI8.0 REC BMS Leaf cells

    The inverter is rated to 9100w for 5 min and 11000w for 3 sec. What size of fuse would be recommended? @ 3.5v (lower than my plan) it will be 11000w/49v=225a. 250a fuse ok? MRBf fuses good stuff? Easy to get hold of 250a of those fuses. NH2 fuse holders are 4 times the price of MRBF holder.
  8. S

    Norwegian 60kwh Powerwall SI8.0 REC BMS Leaf cells

    Hi all, I've been reading alot of the threads and thought it was about time to post about my project, and get some tips/help for my build. Its based on 3 complete Nissan Leaf batteries + 3 modules, giving me 147 modules in a 14S42P setup. I will be using REC BMS and Sunny Island 8.0 battery...
  9. S

    Reverse engineered SIMPbms now working on SMA Sunny Island series

    Hi, Any progress on the sunny boy storage? It would be VERY much cheaper then using Sunny islands. We can through my company get hold of the sunny boy 2.5 for 600gbp ex vat vs 2300 ex vat for the sunny island. 2x sunnyboy would be more than enough for me :) I will be building a 73kwh battery...
  10. S

    Good BMS choice for 48v Nissan Leaf powerwall

    No, 14s28P. Each complete battery consist of 48 modules that each has 2S2P setup.*2 + 2 modules extra gives 392 cells. Each cell is 3.8v/32ah. so 47.6kwh max rated capacity. Will try to include 49 more modules when i get hold of it, to reduce strain on batteries. I normally use about 40-50khw...
  11. S

    Inverter for Nissan Leaf Powerwall

    With Victron setup, you can also use REC BMS with can-bus to the CCGX :)
  12. S

    Good BMS choice for 48v Nissan Leaf powerwall

    Hi, I am building a (for now) 49kwh powerwall using 2 leaf batteries + 2 modules. I am using REC BMS + SMA Sunny Island 8.0H inverter. REC has Can-bus to the battery inverter so everything is integrated ::)